Gallagher's called us in when standard drainer pumps couldn't cope with 15 metres of silt at the bottom of a cofferdam.
The background
The Connaught Tunnel forms part of the Elizabeth line infrastructure in east London and is managed and maintained by Rail for London Infrastructure, part of Transport for London.
The Connaught Crossing was a major rail tunnelling job in east London, with two cofferdams sat about 50 metres apart, between the Royal Albert and Royal Victoria docks. The water between them was pumped out, which left a thick layer of silt and slurry 15 metres down.
The plan was to reach the existing tunnels through the base of the excavation and enlarge them. That meant the bottom of the excavation had to be cleared first.
The problem
The team started with standard diesel-driven hydraulic drainer pumps. They blocked, repeatedly, and every blockage meant stopping to clear them before work could restart. The delays were adding up.
Drainer pumps aren't built to shift heavy slurry with a specific gravity of around 1.3, and it showed.
What we suggested
We came back with a temporary dredging system, and offered to supply all of it. Generators, control gear, cabling, pumps and pipework, so the site had one package to deal with instead of several suppliers to coordinate.
The principle is simple. With high specific gravity material the job is to keep it moving, because anything that stops settles in the pipework. Pump selection is what holds those velocities up. We went with a heavy-duty hard iron pump, which copes with the abrasive and sometimes corrosive conditions you get on a job like this.
We also suggested a jetting ring on the pump to hold a consistent 70/30 water-to-soil mix, and high-pressure jetting to break down the more compacted material where densities varied. The site wanted the system running unmanned, so we automated the Dragflow slurry pump system as well.
How it worked
The dredging pump went in at the deepest point of the excavation, so material would gravitate towards it. A Grindex Master H, suspended in the main dock, delivered water at 3 bar over the 15-metre cofferdam to a tee piece. One spur fed the jetting ring to keep the material agitated. The other fed cooling water to the dredging pump.
That second spur was important. A submersible is normally cooled by whatever it's sitting in, and here we could only get the pump half-submerged. The spray kept the motor within temperature.
Smaller excavators and lightweight dredging pumps that could be moved around easily shifted slurry across the dock floor towards the main pump. From there, a 44kW hard iron dredging pump with an 8-inch discharge sent it 100 metres over the cofferdam through wire armoured hose.
The outcome
Around 6,000m³ of slurry moved over ten weeks, working with intermittent breaks, using between 12,000 and 18,000m³ of water in the mix.
Towards the end we brought in a 37kW Grindex Maxi with level controls, to handle the residual slurry and cofferdam leakage for the rest of the project without anyone needing to watch it.
Kit on the job
- Euroflo hard iron dredging pump, 44kW, 8" discharge, with jetting ring
- Dragflow heavy-duty slurry pump system, automated for unmanned running
- Grindex Master H, for high-pressure jetting and cooling water
- Grindex Maxi 8" drainage pump (37kW) for residual water management
- Generators, control equipment, cabling and pipework
Working on something similar? If you've got a job where the material is heavier than the pumps are happy with, we're glad to talk it through before anyone commits to anything. Email sales@euroflo.com or call 01892 832144.