Three years of continuous cooling water for the TBMs cutting through central London, with a system designed to shut itself down before it could ever run dry.

The background

The Crossrail route runs 118km east from Maidenhead to Abbey Wood, calls at 37 stations, and passes under central London through 21km of twin-bore tunnel.

Those tunnels were cut by tunnel boring machines. A TBM generates a lot of heat, and it needs a constant supply of water to stay within its operating temperature. We were brought in to install the industrial pump system that kept it supplied.

The problem

The water had to reach the machine wherever it happened to be, down a shaft and along a live tunnel, at a flow and pressure the TBM could rely on hour after hour for years.

There isn't much room for interruption. If the water stops, the machine stops, and that holds up the whole excavation behind it.

What we suggested

We proposed a closed circuit. Pumps and storage tanks at ground level, water fed down the shaft and along the tunnel to the machine, then returned through a filtration system back to the tanks.

Each TBM needed 20 litres per second, with 8 l/s used inside the machine and 12 l/s coming back up, at an inlet pressure of anywhere between 4 and 10 bar. We specified 37kW vertical multistage industrial pumps to hold that.

There were two details we pushed for. The first was low level cut-off electrodes in the pipework, which shut the system down the moment water levels drop, protecting the pumps rather than finding out the hard way. The second was skid mounting, so the whole thing could arrive as a package instead of being built on site.

How it worked

The set-up flexed to suit each location. On one site, three TBMs were running at once, so the system delivered 60 l/s from a single 3,200m³ tank with one industrial pump per tunnel. On another, a single TBM needed 20 l/s, supported by an 1,100m³ tank.

Behind the pumps sat an integrated arrangement of pipework, transducers, valves and inverter controls, holding constant flow and pressure to each machine.

Everything was mounted on heavy galvanised steel skids with lifting points, so it could be delivered, craned into place and connected on arrival.

The outcome

The system ran for three years of TBM operation beneath central London. The cut-offs did their job protecting the equipment, and the machines kept cutting.

We were picked for this one on the strength of our experience in industrial pumping, and on how the team works day to day.

Kit on the job

  • 37kW vertical multistage industrial pumps
  • Storage tanks at 3,200m³ and 1,100m³
  • Filtration system for the return circuit
  • Transducers, valves and inverter controls
  • Low level cut-off electrodes
  • Galvanised steel skids with lifting points, modular 'plug and go' build

Working on something similar? If you've got a process that can't afford to stop, we'd rather help you design that in from the start. Email sales@euroflo.com or call 01892 832144.

Get in Touch

Tel: (UK) 01892 832144

Tel: (Eire) 1 410 5730

sale1s@euroflo.com

Our locations

UK Office
Euroflo Fluid Handling Ltd
Wexford place, Lucks Lane
Paddock Wood, Kent
TN12 6PA

Ireland
Unit F1 Baldonnell Business Park
Baldonnell
County Dublin
DUBLIN 22
Ireland

Euroflo are accredited with ISO 9001 as part of our ongoing commitment to quality and excellence in the pumping sector industry

ISO 9001 accreditation

© 2026 | Euroflo Fluid Handling Ltd - registered in England & Wales, reg number: 03205022

Site by Giraffe Design